Operational5.3 MWApplication 12/0906/PASubmitted 21 December 2012Granted on appeal 16 April 2014

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
12/0906/PA
Planning authority
Pembrokeshire
Nation
Wales
Technology
Solar
Capacity
5.3 MW
Status
Operational
Operator or applicant
Elgin Energy EsCo
Location
Land at Wogaston Farm, SA71 5AA
Appeal reference
APP/N6845/A/13/2203220
First operating
2015
  • 21 December 2012 Planning application submitted
  • 27 June 2013 Planning permission refused
  • 27 November 2013 Appeal lodged
  • 16 April 2014 Planning permission granted
  • 16 April 2014 Appeal granted
  • 1 January 2015 Construction started
  • 17 March 2015 Operational

The pack for this site lists 89 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-1541, Transformer unit fire at a solar farm on Copshorn Road, Bodmin, 135 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-15412015Transformer unit fire at a solar farm on Copshorn Road, Bodmin135 kmMinor
EIR-15442014Fire at solar panel installation near Bodmin Jail135 kmMinor
EIR-15332022Solar panel fault causes fire at village hall roof in Cheriton Bishop135 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 86 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near SA71 5AA is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Pembrokeshire.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.