← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Battery storage · Swansea

Swansea Greener Grid Park

Under ConstructionApplication 2021/0163/FULSubmitted 21 January 2021Granted 9 August 2021

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
2021/0163/FUL
Planning authority
Swansea
County or area
West Glamorgan
Nation
Wales
Technology
Battery storage (Stand-alone Storage)
Status
Under Construction
Operator or applicant
Statkraft UK / Swansea Grid Solutions
Location
Land West Of, Rhydypandy Road, Morriston, Swansea, SA6 6NU
  • 21 January 2021 Planning application submitted
  • 9 August 2021 Planning permission granted
  • 1 December 2024 Construction started
  • 9 August 2026 Planning permission expired

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0249, Smoke and fire incident at Battery Box, Pinhoe Road, Exeter, 111 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-02492026Smoke and fire incident at Battery Box, Pinhoe Road, Exeter111 kmSignificant
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire139 kmSignificant
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool202 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near SA6 6NU is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Swansea.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.