Planning application · Onshore wind · East Riding of Yorkshire

Skipsea Lane, Dunnington - Wind Farm

Awaiting Construction4.2 MWApplication 22/00443/STPLFSubmitted 15 March 2022Granted 21 October 2022

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
22/00443/STPLF
Planning authority
East Riding of Yorkshire
Nation
England
Technology
Onshore wind
Capacity
4.2 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Manor Farm Feeds
Location
North Of Manor Farm Wind Turbine Skipsea Lane Dunnington, YO25 8EG
Turbines
1, 149.38 m to tip
  • 15 March 2022 Planning application submitted
  • 21 October 2022 Planning permission granted
  • 21 October 2025 Planning permission expired

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1946, Wind turbine fire sends black smoke across Hull, 22 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-19462022Wind turbine fire sends black smoke across Hull22 kmSignificant
EIR-18102022Wind turbine at Cargill Hull factory damaged by fire22 kmMajor
EIR-09232009Wind turbine blade detaches at Conisholme wind farm in Lincolnshire after bolt failure62 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near YO25 8EG is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in East Riding of Yorkshire.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.