Full planning pack, launch price £145Other options

Planning application · Onshore wind · East Lindsey

Newton Marsh Wind Project

Operational4.6 MWApplication N/178/03348/07Submitted 29 January 2008Granted on appeal 28 May 2009

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
N/178/03348/07
Planning authority
East Lindsey
County or area
Lincolnshire
Nation
England
Technology
Onshore wind
Capacity
4.6 MW
Status
Operational
Operator or applicant
TCI Renewables
Location
Newton Marsh Sewage Treatment Works, Tetney, North-East Lincolnshire
Appeal reference
APP/D2510/A/08/2090543
Turbines
2
First operating
2014
  • 29 January 2008 Planning application submitted
  • 20 May 2008 Planning permission refused
  • 28 May 2009 Planning permission granted
  • 28 May 2009 Appeal granted
  • 25 June 2012 Construction started
  • 30 April 2014 Operational

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0923, Wind turbine blade detaches at Conisholme wind farm in Lincolnshire after bolt failure, 11 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-09232009Wind turbine blade detaches at Conisholme wind farm in Lincolnshire after bolt failure11 kmSignificant
EIR-19462022Wind turbine fire sends black smoke across Hull36 kmSignificant
EIR-18102022Wind turbine at Cargill Hull factory damaged by fire36 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near Newton Marsh Wind Project is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in East Lindsey.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.