← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · Scottish Government (S36)

Mid Hill - Phase II

Operational18.4 MWApplication SO30179PFSubmitted 12 February 2003Granted 3 June 2005

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
SO30179PF
Planning authority
Scottish Government (S36)
County or area
Grampian
Nation
Scotland
Technology
Onshore wind
Capacity
18.4 MW
Status
Operational
Operator or applicant
Fred Olsen Renewables
Location
Mid Hill, Fetteresso Stonehaven
Turbines
8
First operating
2014
  • 12 February 2003 Planning application submitted
  • 3 June 2005 Planning permission granted
  • 25 August 2014 Construction started
  • 2 December 2014 Operational

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1386, Wind turbine fire near St Cyrus in Aberdeenshire, 22 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-13862022Wind turbine fire near St Cyrus in Aberdeenshire22 kmMinor
EIR-04412025Wind turbine collapses at Aviva's Pitheavlis site in Perth86 kmSignificant
EIR-07672024Nordex turbine fire prompts investigation at Scottish wind farm101 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near Mid Hill - Phase II is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Scottish Government (S36).

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.