← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Battery storage · North East Lincolnshire

Mauxhall Farm

Planning Permission Expired24 MWApplication DM/1145/19/FULSubmitted 17 December 2019Granted 21 May 2021

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
DM/1145/19/FUL
Planning authority
North East Lincolnshire
County or area
Humberside
Nation
England
Technology
Battery storage (Co-located with RE)
Capacity
24 MW
Status
Planning Permission Expired
Operator or applicant
ENGIE Renewables
Location
Mauxhall Farm, Immingham Road, Stallingborough, Grimsby, Humberside, DN41 8BS
  • 17 December 2019 Planning application submitted
  • 6 November 2020 Planning permission refused
  • 21 May 2021 Planning permission granted
  • 6 November 2023 Planning permission expired

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0584, Fire in a battery container at Rufford Colliery BESS, Rainworth, caused by a short circuit in NMC cells, 81 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth, caused by a short circuit in NMC cells81 kmSignificant
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool181 kmMajor
EIR-01092025Fire in single battery unit at Thurrock BESS under construction239 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near DN41 8BS is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in North East Lincolnshire.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.