Greenside Extension - Wind Turbines

Awaiting Construction7.1 MWApplication APP/2024/0229Submitted 4 March 2024Granted 27 March 2025

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
APP/2024/0229
Planning authority
Aberdeenshire
Nation
Scotland
Technology
Onshore wind
Capacity
7.1 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Greenside Wind Energy Limited
Location
Overside & Greenwellheads Farms, Crimond, Fraserburgh, Peterhead, AB42 3HJ
Turbines
3, 100 m to tip
  • 4 March 2024 Planning application submitted
  • 27 March 2025 Planning permission granted

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1386, Wind turbine fire near St Cyrus in Aberdeenshire, 96 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-13862022Wind turbine fire near St Cyrus in Aberdeenshire96 kmMinor
EIR-07672024Nordex turbine fire prompts investigation at Scottish wind farm161 kmSignificant
EIR-04412025Wind turbine collapses at Aviva's Pitheavlis site in Perth162 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near AB42 3HJ is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Aberdeenshire.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.