← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · Rugby

Bransford Bridge

Application Refused18 MWApplication R10/2303Submitted 6 June 2011Refused 7 September 2011

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
R10/2303
Planning authority
Rugby
County or area
Warwickshire
Nation
England
Technology
Onshore wind
Capacity
18 MW
Status
Application Refused (Planning Permission Refused)
Operator or applicant
Scottish and Southern Energy (SSE)
Location
n/w of Junction 1, M6, Churchover, Rugby, Warwickshire, CV23
Turbines
9
  • 6 June 2011 Planning application submitted
  • 7 September 2011 Planning permission refused

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-2021, Wind turbine catches fire near Thorney in Lincolnshire, 82 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-20212022Wind turbine catches fire near Thorney in Lincolnshire82 kmSignificant
EIR-15782024Wind turbine fire near Chumleigh in Devon82 kmSignificant
EIR-12752022Fire damages Siemens Gamesa turbine at French Farm wind farm83 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near Bransford Bridge is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Rugby.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.