Enercon E40 turbine nacelle and rotor topple from tower in the Vogelsberg hills near Ulrichstein
Jan 1999Published 24 Nov 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on wind (onshore) incidents in Germany, and an email when EIR-3030 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Enercon
What happened
On 17 January, a failure was reported in March 1999 in which an Enercon E40 500 kW wind turbine at a three-turbine site in the Vogelsberg hills near Ulrichstein had its nacelle and rotor topple off the tower. The turbine was owned by Vogelsberg Windenergie and had been installed in December 1996. The failure happened in winds gusting up to 30 metres per second. The other two machines at the site were working normally but were also being investigated.
Nobody was hurt, as the machines are sited in a field. Enercon replaced the destroyed nacelle and rotor within four days and took the damaged components to its main facility at Aurich for inspection. At the time of reporting, Enercon was still investigating the cause.
Contributing factors
The incident happened in winds gusting up to 30 metres per second. The cause had not been established at the time of reporting and was under investigation by the manufacturer, Enercon.
Lessons learned
- Secure damaged structural components quickly and send them to the manufacturer for inspection, as was done here, so the cause can be established.
- Keep other machines of the same type under review until the cause of a structural failure is known, because the two other turbines at this site were also investigated.
- Consider the distance between turbines and occupied areas, since no one was hurt here, where the machines stood in a field.
More lessons on structural integrity and turbines, spacing, layout and fire spread, from every incident on the register.
Published 2026-11-24. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.