Extreme weather brings down 275kV transmission line, cutting power on Eyre Peninsula
2026Published 20 Nov 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in Australia, and an email when EIR-2970 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): ElectraNet, ENGIE
What happened
Extreme weather brought down a 275kV transmission line on the Eyre Peninsula in South Australia, cutting power to about 24,000 properties in the region. The source describes the weather as a one-in-2000-year event. The towers were built to withstand wind speeds of up to 170 km/h. ElectraNet said it thought the localised weather had been stronger than the winds the towers were designed for. On the Thursday evening, the Australian Energy Market Operator (AEMO) classed the situation as an electricity supply emergency and directed Synergen Power to restart the mothballed Port Lincoln power station, unit POR01, to synchronise and maintain local load and manage frequency control until further notice.
As of Friday afternoon, more than 6,000 properties remained without power. ElectraNet was progressively re-energising areas after visually inspecting the damaged lines. More than 2,700 NBN telecommunications services were also affected on the peninsula.
Contributing factors
ElectraNet said the localised weather appeared to be stronger than the wind speeds the towers were designed to withstand. The source does not report a structural defect and does not state whether the mothballed Port Lincoln units affected the outage. Background from the source: ENGIE removed units POR01 and POR03 from service on 1 July 2024, citing unprofitability, and in January 2025 the Australian Energy Market Commission ruled that the units could be used as emergency backup power sources.
Lessons learned
- Review transmission tower wind design basis against localised extreme weather, since rare events can exceed design values.
- Plan how generation held in reserve, including mothballed plant, can be brought back at short notice in an emergency, as AEMO did here.
- Map dependencies between energy and telecommunications networks, because a redundant communications path can be unavailable when the power supply it relies on fails.
More lessons on weather and external hazards, emergency response and public communication, outages, backup supply and restoration, from every incident on the register.
Source
Published 2026-11-20. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.