Fire at Fairlight substation in East Sussex tackled by firefighters
2019Published 18 Nov 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in the United Kingdom, and an email when EIR-2959 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): UK Power Networks
What happened
SussexWorld reported that firefighters put out a fire at a substation on Meadow Way in Fairlight, East Sussex. East Sussex Fire and Rescue Service was alerted to reports of smoke coming from the substation and mobilised two appliances from Hastings at about 11.05am. Crews used a CO2 extinguisher to put out the fire, made the area safe and left the incident in the hands of UK Power Networks. The article, published on 28 February 2019, does not state the cause of the fire or the equipment involved.
The article gives the day as Tuesday, March 22, which does not match its publication date, so the incident date is not confirmed. A headline on the same page states that more than 1400 homes lost power after the Fairlight substation fire; this is not in the article text and has not been confirmed in the body of the report.
Contributing factors
Not reported.
Lessons learned
- Substation fire detection and smoke alarms should alert the network operator's control room directly, so that isolation can begin before the fire service arrives.
- Fire and rescue services and network operators should agree handover arrangements at the scene so that responsibility for making the equipment safe is clear.
- Operators should record the cause, equipment and customer impact of substation fires, so that similar failures can be identified and addressed across the network.
More lessons on detection and monitoring, from every incident on the register.
Source
Other entries that name Sussex
Published 2026-11-18. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.