EstLink 1 interconnector out of service after fault at Espoo converter station
Sept 2025Published 18 Nov 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in Finland, and an email when EIR-2945 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Fingrid
What happened
Estonian grid operator Elering reported that the EstLink 1 electricity interconnector between Estonia and Finland was out of service because of a fault at the Espoo converter station on the Finnish side. The interruption began at 5:46 on Monday 1 September 2025. Elering cited an initial urgent market message from Fingrid, the Finnish transmission system operator, which said the interconnector would remain out of service until the end of that day's trading on the power exchange.
Elering's report said the duration of the outage might change as more details about the fault became clear. EstLink 1 has a capacity of 350 megawatts and began operating in 2007. The source does not describe the nature of the fault or its cause, and gives no later update on restoration.
Contributing factors
Not reported. The source describes the fault only as occurring at the Espoo converter station on the Finnish side.
Lessons learned
- Operators of interconnectors and converter stations should publish an early outage notice and update the expected restoration time as the fault is diagnosed.
- Transmission operators on both sides of an interconnector should coordinate their market messages so that the outage and its expected duration are reported consistently.
- Converter station faults can remove a large share of cross-border transfer capacity at short notice, so market participants and operators should plan for sudden loss of an interconnector.
More lessons on outages, backup supply and restoration, from every incident on the register.
Source
Published 2026-11-18. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.