Wind farm company fined after employee killed in Sligo landslide
2022Published 13 Nov 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on wind (onshore) incidents in Ireland, and an email when EIR-2893 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
What happened
An employee died after a landslide at a wind farm site in County Sligo, Ireland, according to an Irish Independent report published on 14 October 2022. The company responsible for the wind farm was fined more than €200,000 following the death. The report summary does not give the date of the incident, the name of the site or company, the circumstances of the landslide, or the court in which the fine was imposed. The full article could not be retrieved, so this entry is drawn from the headline and summary only and should be treated as provisional until the full report is checked against other sources.
Lessons learned
- Assess ground stability before and during earthworks on wind farm sites, particularly on sloping ground, and monitor for ground movement after heavy rainfall.
- Establish exclusion zones and early-warning procedures for personnel working below slopes or cut faces.
- Ensure contractors and employees are trained to recognise ground hazards and have clear authority to stop work when conditions change.
More lessons on detection and monitoring, worker safety and safe systems of work, from every incident on the register.
Source
Published 2026-11-13. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.