Register / Data centre / EIR-1878
← Back to the list
Data centreSouth KoreaEIR-1878

Fire at Samsung SDS data centre in Gwacheon during UPS expansion works

Apr 2014Published 2 Oct 2026Updated 13 Oct 2026Responsible editor: Chief Editor

Estimated damageEstimated by the register's adjusterHow? Know the real figure?
Figure hidden: shown to subscribersLow confidence
out of service for about •• daysShown in the record →Full estimate
From the recordRoot cause hiddenFailed part hidden

Companies named in the reporting of this entry (being named is not a finding of fault): Samsung SDS

On Sunday 20 April 2014, a fire broke out at Samsung SDS's data centre in Gwacheon, south of Seoul, while a generator was running to support expansion works on the uninterruptible power supply (UPS). Reports described a fully involved building fire in the four-storey building, and part of its facade fell away due to fire damage. One staff member suffered minor cuts and scratches from debris, and staff were able to evacuate.

The centre ran IT systems for Samsung Group financial affiliates, and data services for Samsung devices worldwide, including smart TVs, phones and tablets, were disrupted for several hours. Affiliates' online card services were halted after the operator shut down servers to guard against data loss, and some salaries had to be paid by branch transfer. Samsung SDS said it was investigating the cause.

A 2023 Supreme Court ruling, reported by Metro Seoul, upheld damages against contractors. The appellate court found that exhaust gas leaking from a welding defect in the generator's flue duct caused the fire. The Supreme Court held that this was not proven beyond reasonable doubt, and did not find that it was absent, so the cause remains disputed. A Financial Supervisory Service inspection found that some financial affiliates kept data on only one server at Gwacheon, rather than on more than two. Samsung Card had started work on a backup centre the previous year, scheduled for completion the following February, and this was not yet in place at the time of the fire.

  1. Treat generator and UPS expansion works in a live data centre as high-risk hot work, with exhaust and flue routes inspected and welds verified before the generator is run.
  2. Keep live copies of critical data at more than one site so that a single building fire does not remove service or data.
  3. Build and test a backup site before major works begin, not after, and agree in advance how customers and affiliates are notified when services are halted.

More lessons on outages, backup supply and restoration, from every incident on the register.

Published 2026-10-02. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

See the register's stories first in Google: add it as a preferred source.

Chart to reuse with this story: Data centre incidents in South Korea, by year, free with a credit (PNG).

Data centre incidents in South Korea: 9 entries, with a free alert for the next one.

See UPS and battery room fires at data centres and backup generator failures at data centres.

Browse the full register or submit an incident.