Rooftop solar fire damages warehouse in Towaco, New Jersey
Mar 2024Published 28 Sept 2026Responsible editor: Chief Editor
- Where
- Corporate Mailings warehouse in Towaco, New Jersey
- Manufacturer
- Tigo Energy
- What
- Fire damaged rooftop solar system on 15 March 2024
- Cause
- Not reported
- Outcome
- Insurer paid more than 236000 US dollars
Get the next one by email
Free alerts on solar PV incidents in the United States, and an email when EIR-1452 is updated. No account needed; unsubscribe in one click.
Confirm your email and every solar incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Advanced Solar Products, Corporate Mailings, Tigo Energy
What happened
On 15 March 2024 a fire damaged a warehouse in Towaco, New Jersey that had a rooftop solar system, according to a subrogation complaint reported by Insurance Business. Advanced Solar Products had designed, procured and built the system in 2021 using TS4-A-2F rapid shutdown devices made by Tigo Energy. The insurer says it paid its insured, Corporate Mailings, more than 236,000 dollars and is seeking more than 241,000 dollars, including a 5,000 dollar deductible.
The complaint, which has not been tested in court, alleges that about seven rapid shutdown devices showed thermal damage within the first eight months and that a 2022 inspection did not raise possible signal interference between devices and inverters.
Contributing factors
The complaint alleges early improper string readings and thermal damage to rapid shutdown devices. It also alleges that a 2020 product manual did not warn about connector types to limit crosstalk, and that this was not raised at a November 2022 inspection. These points have not been tested in court.
Lessons learned
- Abnormal string readings should prompt an early check of rapid shutdown devices for thermal damage.
- Installation instructions should make clear any connector and string layout requirements intended to limit electromagnetic interference.
- After an early component fault, follow-up should record what was checked and what remains unresolved before the system stays in service.
More lessons on spacing, layout and fire spread, from every incident on the register.
Not yet known
- Cause of the fire
- Turbine model and age
- Cost of the damage
- Downtime after the fire
This entry is updated when these are reported. Get an alert for the next one like it.
Source
Published 2026-09-28. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.