Grid infrastructureMozambiqueEIR-1354

Fire at Munhava substation causes blackout in Beira

2023Published 28 Sept 2026

A fire destroyed much of the electricity substation in the Munhava neighbourhood of Beira on a Saturday morning. The publicly owned electricity company EDM said the resulting power cut left more than 160,000 of its clients without supply. Alternative power kept key sites, including Beira Central Hospital and the city's international airport, operating. After the fire was brought under control, technical teams worked to restore normal supplies. The causes of the fire were not known at the time of the report.

  1. Alternative supplies for hospitals, airports and other critical sites limit the effect of a substation fire.
  2. Restoration planning should start as soon as the fire is under control.
  3. Early reports may not identify the cause, so operators should not treat the first public account as a completed investigation.

Published 2026-09-28. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

Get the next one like this

One email when a newly reported incident is confirmed, at most two a day, plus a Monday digest. Free, no account needed, unsubscribe in one click.

By subscribing you agree to the privacy policy.

Related incidents

Browse the full register or submit an incident.