Faulty blade causes turbine collapse at Chatham-Kent wind farm
2018Published 15 Sept 2026Responsible editor: Chief Editor
- Where
- Raleigh wind facility in Chatham-Kent, Ontario
- Operator
- TerraForm
- What
- wind turbine snapped in half and collapsed
- Cause
- single faulty blade
- Outcome
- halted all 70 turbines for nearly two months, cost $6 million
Get the next one by email
Free alerts on wind (onshore) incidents in Canada, and an email when EIR-0814 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): TerraForm
What happened
In January 2018, a wind turbine at the Raleigh wind facility in Chatham-Kent, Ontario, snapped in half and collapsed. The site operator, TerraForm, said the failure was caused by a single faulty blade. Following the collapse, the company halted operation of all 70 turbines at the facility for nearly two months to carry out safety inspections across the fleet. TerraForm's first quarter results stated the incident cost the company about $6 million in cash that would otherwise have been distributed to shareholders. The company said its subsequent investigation found no similar issues with the remaining turbines before returning the wind farm to service.
Contributing factors
A single faulty blade was identified by the operator as the cause of the turbine failure, prompting a precautionary fleet-wide inspection of all 70 turbines at the site.
Lessons learned
- A faulty blade on a wind turbine can cause collapse, so operators should check all blades at the site after one failure.
- One turbine collapse at a wind farm can force inspection of the full fleet, so owners should plan for two months of lost output.
- A single blade fault at a wind farm can cost millions in lost revenue, so insurers should model full site shutdowns in risk plans.
More lessons on structural integrity and turbines, from every incident on the register.
Not yet known
- Turbine model and age
- Exact nature of the blade fault
- Time to return each turbine to service
This entry is updated when these are reported. Get an alert for the next one like it.
Source
Site page: Raleigh (status, dates and other incidents)
Published 2026-09-15. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.