Onshore wind · United Kingdom
West Garty Windfarm
Operator West Garty Renewables
Appeal Refused54 MWData checked 16 November 2026Source record dated 27 November 2018
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
West Garty Windfarm is a 54 MW wind farm 53 km north-west of Lossiemouth, Highland, United Kingdom. Its planning application (EC00002075) went to Scottish Government (S36) on 1 December 2014 and was refused on appeal on 19 October 2018. Its status in the Renewable Energy Planning Database (UK government) is appeal refused. There are 7 other energy sites within 10 km, 5 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when West Garty Windfarm changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 54 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Appeal Refused
- Operator or applicant
- West Garty Renewables
- Location
- West Garty Estate, Helmsdale, East Sutherland, Highland, KW8 6HP, United Kingdom
- Planning authority
- Scottish Government (S36)
- Planning application
- EC00002075
- Appeal reference
- WIN-270-6
- Turbines
- 18, 120 m to tip
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for EC00002075, with what the planning evidence pack adds for this site.
Every application in Scottish Government (S36) · Alerts for applications and incidents near here
Timeline
- 1 December 2014 Planning application submitted
- 17 May 2016 Appeal lodged
- 19 October 2018 Planning permission refused
- 19 October 2018 Appeal refused
Incidents on the register at this site
None found. The register holds no published incident that names West Garty Windfarm. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has West Garty Windfarm had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names West Garty Windfarm; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of West Garty Windfarm?
- Appeal Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 27 November 2018.
- Where is West Garty Windfarm?
- 53 km north-west of Lossiemouth, Highland, United Kingdom (postcode KW8 6HP).
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).