Vine Farm Solar Park

Operational45 MWChecked 6 October 2026Last changed in the dataset 2 February 2017

Technology
Solar
Capacity
45 MW
Status
Operational
Operator or applicant
Allianz
Location
Vine House, Vine Farm, High Street, Shingay Cum Wendy, Royston, Cambridgeshire, SG8 0HJ, United Kingdom
Planning authority
South Cambridgeshire
Planning application
S/1067/14/FL
First operating
2016

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 9 May 2014 Planning application submitted
  • 6 August 2014 Secretary of State intervened
  • 2 September 2014 Granted by the Secretary of State
  • 1 August 2015 Construction started
  • 15 March 2016 Operational

None found. The register holds no published incident that names Vine Farm Solar Park. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.