Torr Works

Operator Aggregate Industries UK

Appeal Refused3.6 MWData checked 16 November 2026Source record dated 7 January 2015

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Torr Works is a 3.6 MW wind farm 6.9 km west of Frome, Somerset, United Kingdom. Its planning application (2013/1244) went to Somerset on 24 June 2013 and was refused on appeal on 25 January 2016. Its status in the Renewable Energy Planning Database (UK government) is appeal refused. There are 29 other energy sites within 10 km, one of them a wind farm. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

429 energy sites within 40 km for Torr Works

Members see the sites and incidents around this one, and every record behind them.

Technology
Onshore wind
Capacity
3.6 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Appeal Refused
Operator or applicant
Aggregate Industries UK
Location
Land adjacent Torr Works, Somerset, United Kingdom
Planning authority
Somerset
Planning application
2013/1244
Appeal reference
APP/Q3305/A/14/2227407
Turbines
4

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 2013/1244, with what the planning evidence pack adds for this site.

Every application in Somerset · Alerts for applications and incidents near here

  • 24 June 2013 Planning application submitted
  • 16 April 2014 Planning permission refused
  • 4 November 2014 Appeal lodged
  • 25 January 2016 Appeal refused

None found. The register holds no published incident that names Torr Works. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Torr Works had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Torr Works; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Torr Works?
Appeal Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 7 January 2015.
Where is Torr Works?
6.9 km west of Frome, Somerset, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).