Stony Energy Storage Facility

Operational79.9 MWChecked 6 October 2026Last changed in the dataset 28 May 2024

Technology
Battery storage (Stand-alone Storage)
Capacity
79.9 MW
Status
Operational
Operator or applicant
Gore Street Energy Storage Fund
Location
Land to the south west of Stony Stratford Substation, south of Stratford Road, Milton Keynes, Buckinghamshire, MK19 6DZ, United Kingdom
Planning authority
Buckinghamshire
Planning application
17/02259/APP
First operating
2023

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 14 July 2017 Planning application submitted
  • 3 September 2021 Planning permission granted
  • 1 July 2022 Construction started
  • 31 July 2023 Operational

None found. The register holds no published incident that names Stony Energy Storage Facility. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.