Solar · United Kingdom

South of Henley Hall

Operational5 MWChecked 6 October 2026Last changed in the dataset 2 March 2018

Technology
Solar
Capacity
5 MW
Status
Operational
Operator or applicant
NESF (formerly Kronos Solar (KS SPV39))
Location
Henley Hall, Ludlow Road, Clee Hill, Shropshire, SY8 3HD, United Kingdom
Planning authority
Shropshire
Planning application
15/01472/FUL
Appeal reference
APP/L3245/W/15/3132946
First operating
2017

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 2 April 2015 Planning application submitted
  • 12 August 2015 Planning permission refused
  • 4 November 2015 Appeal lodged
  • 8 June 2016 Planning permission granted
  • 8 June 2016 Appeal granted
  • 15 December 2016 Construction started
  • 17 March 2017 Operational

None found. The register holds no published incident that names South of Henley Hall. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.