← Back to Bedfordshire

Energy sites / United Kingdom / Bedfordshire

Battery storage · United Kingdom

Pumping Station - Micro Energy Storage

Awaiting Construction0.2 MWChecked 6 October 2026Last changed in the dataset 18 November 2024

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
AMP Energy Services Limited
Location
Pumping Station, Johnson Drive, Leighton Buzzard, Bedfordshire, LU7 4RT, United Kingdom
Planning authority
Central Bedfordshire
Planning application
CB/24/02337/FULL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 5 September 2024 Planning application submitted
  • 12 November 2024 Planning permission granted

None found. The register holds no published incident that names Pumping Station - Micro Energy Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.