Onshore wind · United Kingdom
Power Generation Development in Claudy
Awaiting Construction0.3 MWChecked 6 October 2026Last changed in the dataset 10 July 2026
The site
- Technology
- Onshore wind
- Capacity
- 0.3 MW
- Status
- Awaiting Construction (Planning Permission Granted)
- Operator or applicant
- Tree Top Farms
- Location
- Lands 215m South West of 334 Longland Road, Claudy, Co. Derry & Strabane, BT47 4AJ, United Kingdom
- Planning authority
- Causeway Coast and Glens
- Planning application
- LA11/2022/0873/F
- Turbines
- 1
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
Timeline
- 15 September 2022 Planning application submitted
- 12 June 2026 Planning permission granted
- 12 June 2031 Planning permission expired
Incidents on the register at this site
None found. The register holds no published incident that names Power Generation Development in Claudy. If you know of one, report it (confidential reports are anonymised).
Follow Power Generation Development in Claudy
Get one email when this site's status changes in the Renewable Energy Planning Database (UK government), or when the register publishes an incident that names it. Free, no account needed, unsubscribe in one click.
By following you agree to the privacy policy.
Incidents at onshore wind farms in the United Kingdom
The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.
Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.