Battery storage · United Kingdom

Pelham

Operational49 MWChecked 6 October 2026Last changed in the dataset 3 January 2019

Technology
Battery storage (Stand-alone Storage)
Capacity
49 MW
Status
Operational
Operator or applicant
Statera Energy/ InfraRed Capital
Location
LAND NORTH OF PELHAM SUBSATION AND SOUTH OF BERDEN ROAD, BERDEN, BISHOP’S STORTFORD, Essex, CM23 1BA, United Kingdom
Planning authority
Uttlesford
Planning application
UTT/16/2316/FUL
First operating
2017

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 16 August 2016 Planning application submitted
  • 15 January 2017 Construction started
  • 15 June 2017 Operational

None found. The register holds no published incident that names Pelham. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents