Osbaldwick Substation

Operational49.9 MWChecked 6 October 2026Last changed in the dataset 30 May 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Operational
Operator or applicant
UK Battery Storage
Location
Os Field 5070, Hull Road, Dunnington, York, North Yorkshire, YO19 5L, United Kingdom
Planning authority
York
Planning application
20/01515/REM
First operating
2024

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 21 August 2020 Planning application submitted
  • 8 October 2020 Planning permission granted
  • 1 May 2022 Construction started
  • 1 January 2024 Operational

None found. The register holds no published incident that names Osbaldwick Substation. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.