Llys Dymper Wind Farm

Operator Windpower Wales

Appeal Withdrawn23 MWData checked 16 November 2026Source record dated 9 December 2015

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Llys Dymper Wind Farm is a 23 MW wind farm 18 km south-west of Denbigh, Clwyd, United Kingdom. Its planning application (0/38695) went to Conwy on 16 February 2012 and was refused on 9 April 2014. Its status in the Renewable Energy Planning Database (UK government) is appeal withdrawn. There are 7 other energy sites within 10 km. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 1 other site and 70 energy sites within 40 km for Llys Dymper Wind Farm

Members see the sites and incidents around this one, and every record behind them.

Technology
Onshore wind
Capacity
23 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Appeal Withdrawn
Operator or applicant
Windpower Wales
Location
Land at Llys Dymper, Gwytherin, Llanrwst, Conwy, Clwyd, United Kingdom
Planning authority
Conwy
Planning application
0/38695
Appeal reference
APP/T6905/A/14/2228788
Turbines
10

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 0/38695, with what the planning evidence pack adds for this site.

Every application in Conwy · Alerts for applications and incidents near here

  • 16 February 2012 Planning application submitted
  • 9 April 2014 Planning permission refused
  • 23 January 2015 Appeal lodged
  • 9 March 2015 Appeal withdrawn

None found. The register holds no published incident that names Llys Dymper Wind Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Llys Dymper Wind Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Llys Dymper Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Llys Dymper Wind Farm?
Appeal Withdrawn, in the Renewable Energy Planning Database (UK government), where it last changed on 9 December 2015.
Where is Llys Dymper Wind Farm?
18 km south-west of Denbigh, Clwyd, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).