Lilbourne Wind Farm

Operational10 MWChecked 6 October 2026Last changed in the dataset 22 April 2015

Technology
Onshore wind
Capacity
10 MW
Status
Operational
Operator or applicant
Cetis
Location
Lilbourne Fields Farm & Lilbourne Lodge Farm, Yelvertoft Road, Lilbourne, Northamptonshire, Northamptonshire, CV23 0SZ, United Kingdom
Planning authority
West Northamptonshire
Planning application
DA/2009/0731
Appeal reference
APP/Y2810/A/11/2164759
First operating
2014
Turbines
5

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 15 October 2009 Planning application submitted
  • 12 October 2011 Planning permission refused
  • 6 July 2012 Planning permission granted
  • 6 July 2012 Appeal granted
  • 18 February 2014 Construction started
  • 15 December 2014 Operational

None found. The register holds no published incident that names Lilbourne Wind Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.