Lamby Way Solar Farm

Operational8.9 MWChecked 6 October 2026Last changed in the dataset 12 January 2021

Technology
Solar
Capacity
8.9 MW
Status
Operational
Operator or applicant
Cardiff Council
Location
Former Lamby Way landfill site, Lamby Way, Rumney, Cardiff, South Glamorgan, South Glamorgan, CF3 2HP, United Kingdom
Planning authority
Cardiff
Planning application
19/00397/MJR
First operating
2020

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 22 February 2019 Planning application submitted
  • 10 May 2019 Planning permission granted
  • 26 November 2019 Construction started
  • 1 May 2020 Operational

None found. The register holds no published incident that names Lamby Way Solar Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents