← Back to Leicestershire

Energy sites / United Kingdom / Leicestershire

Solar · United Kingdom

Hall Farm Solar Farm (Newbold Verdon)

Operational5 MWChecked 6 October 2026Last changed in the dataset 18 July 2016

Technology
Solar
Capacity
5 MW
Status
Operational
Operator or applicant
Push Energy/ NextEnergy Solar Fund (NESF)
Location
Hall Farm, Main Street, Newbold Verdon, LEICESTER, LE9 9NL, Leicestershire, United Kingdom
Planning authority
Hinckley and Bosworth
Planning application
14/00660/FUL
First operating
2015

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 17 July 2014 Planning application submitted
  • 3 June 2015 Planning permission granted
  • 7 September 2015 Construction started
  • 8 December 2015 Operational

None found. The register holds no published incident that names Hall Farm Solar Farm (Newbold Verdon). If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.