Gruig Wind Farm

Operator Foresight Group · Owner Foresight Holdco 2 LTD

Operational25 MWData checked 20 November 2026Source record dated 5 November 2019

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Gruig Wind Farm is a 25 MW wind farm 15 km east of Ballymoney, Co. Antrim, United Kingdom. Its planning application (D/2004/0790/F) went to Causeway Coast and Glens on 18 October 2004 and was granted on 25 June 2007. It has been operating since 27 January 2009. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 15 other energy sites within 10 km, 14 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 2 other sites and 146 energy sites within 40 km for Gruig Wind Farm

Members see the sites and incidents around this one, and every record behind them.

FORESIGHT GROUP LLP (OC300878), active, since 2001. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Onshore wind
Capacity
25 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Foresight Group
Owner
Foresight Holdco 2 LTD
Location
Gruig, Corkey, nr Cloughmills, Co. Antrim, Co. Antrim, United Kingdom
Planning authority
Causeway Coast and Glens
Planning application
D/2004/0790/F
First operating
2009
Turbines
10

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for D/2004/0790/F, with what the planning evidence pack adds for this site.

Every application in Causeway Coast and Glens · Alerts for applications and incidents near here

  • 18 October 2004 Planning application submitted
  • 25 June 2007 Planning permission granted
  • 27 January 2009 Operational

None found. The register holds no published incident that names Gruig Wind Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Gruig Wind Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Gruig Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Gruig Wind Farm?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 5 November 2019.
Where is Gruig Wind Farm?
15 km east of Ballymoney, Co. Antrim, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).