Corkey Wind Farm Extension

Operational2.5 MWChecked 6 October 2026Last changed in the dataset 14 July 2017

Technology
Onshore wind
Capacity
2.5 MW
Status
Operational
Operator or applicant
Northern Ireland Renewables
Location
583m north of 42 Reservoir Road, Knockagallen, Corkey., Co. Antrim, United Kingdom
Planning authority
Causeway Coast and Glens
Planning application
D/2010/0060/F
First operating
2017
Turbines
1

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 19 February 2010 Planning application submitted
  • 10 February 2012 Planning permission granted
  • 13 April 2017 Construction started
  • 13 July 2017 Operational

None found. The register holds no published incident that names Corkey Wind Farm Extension. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.