← Back to Northamptonshire

Energy sites / United Kingdom / Northamptonshire

Battery storage · United Kingdom

Grendon Lakes, Grendon - Battery Storage Facility

Awaiting Construction50 MWChecked 6 October 2026Last changed in the dataset 19 May 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
50 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Statera Energy
Location
Grendon Lakes, Main Road, Grendon, Northampton, Northamptonshire, NN7 1JW, United Kingdom
Planning authority
North Northamptonshire
Planning application
NW/23/00360/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 29 June 2023 Planning application submitted
  • 29 July 2025 Planning permission granted
  • 29 July 2028 Planning permission expired

None found. The register holds no published incident that names Grendon Lakes, Grendon - Battery Storage Facility. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.