← Back to Buckinghamshire

Energy sites / United Kingdom / Buckinghamshire

Battery storage · United Kingdom

East Claydon Battery Energy Storage

Awaiting Construction500 MWChecked 6 October 2026Last changed in the dataset 30 September 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
500 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Statera Energy
Location
Rookery Farm, Granborough, Buckingham, Buckinghamshire, MK18 3NJ, United Kingdom
Planning authority
Buckinghamshire
Planning application
23/03875/APP

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 15 December 2023 Planning application submitted
  • 20 December 2024 Planning permission refused
  • 11 September 2025 Appeal granted

None found. The register holds no published incident that names East Claydon Battery Energy Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.