Goonhilly Downs Wind Farm Repower

Operational12 MWChecked 6 October 2026Last changed in the dataset 4 July 2012

Technology
Onshore wind
Capacity
12 MW
Status
Operational
Operator or applicant
REG Windpower (previously Cornwall Light & Power)
Location
Goonhilly Downs Wind Farm, Bonython Manor, Cury Cross Lanes, Helston, Cornwall, TR12 7BA, Cornwall, United Kingdom
Planning authority
Cornwall
Planning application
PA07/02103/FM
First operating
2010
Turbines
6

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 21 December 2007 Planning application submitted
  • 4 August 2008 Planning permission granted
  • 1 August 2010 Construction started
  • 1 November 2010 Operational

None found. The register holds no published incident that names Goonhilly Downs Wind Farm Repower. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.