← Back to Cumbria

Energy sites / United Kingdom / Cumbria

Onshore wind · United Kingdom

Furness Wind Farm/High Winds (Harlock Repowering)

Operational11.5 MWChecked 6 October 2026Last changed in the dataset 4 June 2020

Technology
Onshore wind
Capacity
11.5 MW
Status
Operational
Operator or applicant
Baywind Co-op & Energy4All & Belltown Power
Location
Standish Cote & Mean Moor, Pennington, Marton & Harlock Hill, Ulverston, Cumbria, Cumbria, LA12 0, United Kingdom
Planning authority
Westmorland and Furness
Planning application
B06/2011/0662
First operating
2016
Turbines
5

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 6 September 2011 Planning application submitted
  • 21 May 2013 Planning permission refused
  • 24 July 2014 Planning permission granted
  • 24 July 2014 Appeal granted
  • 20 December 2015 Construction started
  • 17 November 2016 Operational

None found. The register holds no published incident that names Furness Wind Farm/High Winds (Harlock Repowering). If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.