← Back to Bedfordshire

Solar · United Kingdom

Faldo Farm

Operator Faldo Solar Farm Ltd

Application Refused10.8 MWData checked 16 November 2026Source record dated 6 November 2014

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Faldo Farm is a 10.8 MW solar farm 5.1 km south-east of Flitwick, Bedfordshire, United Kingdom. Its planning application (CB/14/02447/FULL) went to Central Bedfordshire on 2 July 2014 and was refused on 25 September 2014. Its status in the Renewable Energy Planning Database (UK government) is application refused. There are 39 other energy sites within 10 km, 15 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.

625 energy sites within 40 km for Faldo Farm

Members see the sites and incidents around this one, and every record behind them.

Technology
Solar
Capacity
10.8 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Application Refused (Planning Permission Refused)
Operator or applicant
Faldo Solar Farm Ltd
Location
Faldo Farm, Faldo Road, Barton-le-Clay, Bedford, Bedfordshire, MK45 4RF, United Kingdom
Planning authority
Central Bedfordshire
Planning application
CB/14/02447/FULL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for CB/14/02447/FULL, with what the planning evidence pack adds for this site.

Every application in Central Bedfordshire · Alerts for applications and incidents near here

  • 2 July 2014 Planning application submitted
  • 25 September 2014 Planning permission refused

None found. The register holds no published incident that names Faldo Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Faldo Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Faldo Farm; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Faldo Farm?
Application Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 6 November 2014.
Where is Faldo Farm?
5.1 km south-east of Flitwick, Bedfordshire, United Kingdom (postcode MK45 4RF).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).