Onshore wind · United Kingdom
Earlseat
Operator The Renewables Infrastructure Group (TRIG)
Operational18.4 MWData checked 16 November 2026Source record dated 20 August 2014
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Earlseat is a 18.4 MW wind farm 3.9 km west of Methil, Fife, United Kingdom. Its planning application (10/03539/EIA) went to Fife on 17 September 2010 and was granted on 2 March 2012. It has been operating since 30 July 2014. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 44 other energy sites within 10 km, 8 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Earlseat changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 18.4 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- The Renewables Infrastructure Group (TRIG)
- Location
- Earlseat Farm Standing Stane Road Kirkcaldy Fife KY1 4TH, Fife, United Kingdom
- Planning authority
- Fife
- Planning application
- 10/03539/EIA
- First operating
- 2014
- Turbines
- 8
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 10/03539/EIA, with what the planning evidence pack adds for this site.
Every application in Fife · Alerts for applications and incidents near here
Timeline
- 17 September 2010 Planning application submitted
- 2 March 2012 Planning permission granted
- 30 October 2013 Construction started
- 30 July 2014 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Earlseat. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Earlseat had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Earlseat; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Earlseat?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 20 August 2014.
- Where is Earlseat?
- 3.9 km west of Methil, Fife, United Kingdom.