Dunbar Grid Substation - Battery Storage

Awaiting Construction49.9 MWChecked 6 October 2026Last changed in the dataset 22 October 2024

Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
FRV TH Powertek Limited
Location
The N/O Dunbar Grid Substation, Dunbar, East Lothian, EH42 1RG, United Kingdom
Planning authority
East Lothian
Planning application
23/01519/PM

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 15 January 2024 Planning application submitted
  • 1 October 2024 Planning permission granted
  • 1 October 2027 Planning permission expired

None found. The register holds no published incident that names Dunbar Grid Substation - Battery Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.