Onshore wind · United Kingdom
Clauchrie Windfarm
Operator ScottishPower Renewables · Owner Scottishpower Renewable Energy Limited
Application Refused100 MWData checked 16 November 2026Source record dated 12 September 2023
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Clauchrie Windfarm is a 100 MW wind farm 14 km south-east of Girvan, Ayrshire, United Kingdom. Its planning application (ECU00002001) went to Scottish Government (S36) on 18 December 2019 and was refused on 31 August 2023. Its status in the Renewable Energy Planning Database (UK government) is application refused. There are 8 other energy sites within 10 km, 5 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Clauchrie Windfarm changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The company behind this site
SCOTTISHPOWER RENEWABLES (UK) LIMITED (NI028425), active, since 1994. 3 outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.
Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.
The site
- Technology
- Onshore wind
- Capacity
- 100 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Application Refused (Planning Permission Refused)
- Operator or applicant
- ScottishPower Renewables
- Owner
- Scottishpower Renewable Energy Limited
- Location
- Land 6km north east of Barhill, South Ayrshire and Dumfries and Galloway, Ayrshire, United Kingdom
- Planning authority
- Scottish Government (S36)
- Planning application
- ECU00002001
- Turbines
- 18, 200 m to tip
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for ECU00002001, with what the planning evidence pack adds for this site.
Every application in Scottish Government (S36) · Alerts for applications and incidents near here
Timeline
- 18 December 2019 Planning application submitted
- 31 August 2023 Planning permission refused
Incidents on the register at this site
None found. The register holds no published incident that names Clauchrie Windfarm. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Clauchrie Windfarm had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Clauchrie Windfarm; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Clauchrie Windfarm?
- Application Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 12 September 2023.
- Where is Clauchrie Windfarm?
- 14 km south-east of Girvan, Ayrshire, United Kingdom.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).