← Back to Dorset

Energy sites / United Kingdom / Dorset

Battery storage · United Kingdom

Buckland Battery Storage

Application Refused150 MWChecked 6 October 2026Last changed in the dataset 4 December 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
150 MW
Status
Application Refused (Planning Permission Refused)
Operator or applicant
REWE 5 Limited (Recurrent Energy and Windel Energy)
Location
S/O Nottington Lane, Tatton, Weymouth, Dorset, DT3 4BU, United Kingdom
Planning authority
Dorset
Planning application
P/FUL/2024/04993

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 2 September 2024 Planning application submitted
  • 18 July 2025 Planning permission refused

None found. The register holds no published incident that names Buckland Battery Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.