Onshore wind · United Kingdom
Brockholes Wind Cluster
Operator Brockholes Farm
Operational2.4 MWData checked 16 November 2026Source record dated 3 June 2013
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Brockholes Wind Cluster is a 2.4 MW wind farm 21 km south-east of Dunbar, Borders, United Kingdom. Its planning application (09/00516/FUL) went to Scottish Borders on 14 April 2009 and was granted on 10 May 2010. It has been operating since 18 February 2013. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 22 other energy sites within 10 km, 18 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Brockholes Wind Cluster changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 2.4 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- Brockholes Farm
- Location
- Brockholes Farm, Grantshouse, Duns, Borders. TD11 3RL, Borders, United Kingdom
- Planning authority
- Scottish Borders
- Planning application
- 09/00516/FUL
- First operating
- 2013
- Turbines
- 3
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 09/00516/FUL, with what the planning evidence pack adds for this site.
Every application in Scottish Borders · Alerts for applications and incidents near here
Timeline
- 14 April 2009 Planning application submitted
- 10 May 2010 Planning permission granted
- 28 February 2012 Construction started
- 18 February 2013 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Brockholes Wind Cluster. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Brockholes Wind Cluster had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Brockholes Wind Cluster; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Brockholes Wind Cluster?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 3 June 2013.
- Where is Brockholes Wind Cluster?
- 21 km south-east of Dunbar, Borders, United Kingdom.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).