Onshore wind · United Kingdom
Brightenber Hill
Appeal Refused7.5 MWChecked 6 October 2026Last changed in the dataset 3 March 2016
The site
- Technology
- Onshore wind
- Capacity
- 7.5 MW
- Status
- Appeal Refused
- Operator or applicant
- Energiekontor UK
- Location
- Land adjacent to Brightenber Hill near Stainton Hall, Gargrave, Skopton, North Yorkshire, BD23 3PA, United Kingdom
- Planning authority
- North Yorkshire
- Planning application
- 05/2012/12568
- Appeal reference
- APP/C2708/A/12/2186488
- Turbines
- 3
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
Timeline
- 17 April 2012 Planning application submitted
- 5 September 2012 Planning permission refused
- 16 December 2014 Appeal lodged
- 10 February 2016 Appeal refused
Incidents on the register at this site
None found. The register holds no published incident that names Brightenber Hill. If you know of one, report it (confidential reports are anonymised).
Follow Brightenber Hill
Get one email when this site's status changes in the Renewable Energy Planning Database (UK government), or when the register publishes an incident that names it. Free, no account needed, unsubscribe in one click.
By following you agree to the privacy policy.
Incidents at onshore wind farms in the United Kingdom
The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.