← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Solar · Herefordshire, County of

Sinton End Farm, Acton Beauchamp - Solar Farm

Application Refused20 MWApplication P243282/FSubmitted 22 July 2025Refused 9 October 2025

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
P243282/F
Planning authority
Herefordshire, County of
County or area
Herefordshire
Nation
England
Technology
Solar
Capacity
20 MW
Status
Application Refused (Planning Permission Refused)
Operator or applicant
Sintons End Solar Farm Limited
Location
Sinton End Farm, Acton Beauchamp, Worcester, WR6 5AE
  • 22 July 2025 Planning application submitted
  • 9 October 2025 Planning permission refused

The pack for this site lists 89 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-1551, Fire involving solar panels on a garage roof in Shropshire, 31 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-15512019Fire involving solar panels on a garage roof in Shropshire31 kmMinor
EIR-12722022Fire in solar panel distribution board at Birmingham college55 kmMinor
EIR-15472025Small fire within a solar panel at a house in Shropshire58 kmMinor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 86 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near WR6 5AE is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Herefordshire, County of.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.