← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Battery storage · Scottish Government (S36)

Shepherd's Rig Wind Farm

Awaiting Construction6 MWApplication ECU00000735Submitted 17 December 2018Granted 21 August 2023

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
ECU00000735
Planning authority
Scottish Government (S36)
County or area
Dumfries and Galloway
Nation
Scotland
Technology
Battery storage (Co-located with RE)
Capacity
6 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Boralex/Infinergy
Location
Shepherds Rig Windfarm 5KM E/O, Carsphairn, Castle Douglas, Dumfries and Galloway, DG7
  • 17 December 2018 Planning application submitted
  • 21 August 2023 Planning permission granted
  • 21 August 2028 Planning permission expired Date as recorded in the register

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0638, Explosion and prolonged fire at Orsted battery storage site in Liverpool, 218 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool218 kmMajor
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth, caused by a short circuit in NMC cells306 kmSignificant
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire417 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near DG7 is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Scottish Government (S36).

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.