← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Battery storage · Herefordshire, County of

Peterstow Gas Compressor Station, Hentland - Energy Storage System

Awaiting Construction49.9 MWApplication P231390/FSubmitted 2 May 2023Granted 19 March 2025

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
P231390/F
Planning authority
Herefordshire, County of
County or area
Herefordshire
Nation
England
Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Novus Renewable Services Limited
Location
S/O Peterstow Gas Compressor Station, Hentland, Ross on Wye, HR9 6AX
  • 2 May 2023 Planning application submitted
  • 19 March 2025 Planning permission granted
  • 19 March 2028 Planning permission expired Date as recorded in the register

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0058, Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire, 55 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire55 kmSignificant
EIR-02492026Smoke and fire incident at Battery Box, Pinhoe Road, Exeter142 kmSignificant
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool166 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near HR9 6AX is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Herefordshire, County of.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.