← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Battery storage · Wiltshire

Melksham Substation East Storage

Operational50 MWApplication 17/04110/FULSubmitted 10 May 2017Granted 26 April 2019

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
17/04110/FUL
Planning authority
Wiltshire
Nation
England
Technology
Battery storage (Stand-alone Storage)
Capacity
50 MW
Status
Operational
Operator or applicant
Statera Energy / Melksham East Storage
Location
Land to the south of Melksham Substation Westlands Farm Westlands Lane Whitley Melksham, SN12 7QG
First operating
2022
  • 10 May 2017 Planning application submitted
  • 26 April 2019 Planning permission granted
  • 1 January 2022 Construction started
  • 7 November 2022 Operational

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0058, Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire, 38 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire38 kmSignificant
EIR-02492026Smoke and fire incident at Battery Box, Pinhoe Road, Exeter118 kmSignificant
EIR-01092025Fire in single battery unit at Thurrock BESS under construction178 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near SN12 7QG is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Wiltshire.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.