← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · Gwynedd

Bodelith Isaf Wind Turbines

Application Refused5 MWApplication C14/0291/04/LLSubmitted 9 April 2014Refused 19 October 2015

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
C14/0291/04/LL
Planning authority
Gwynedd
Nation
Wales
Technology
Onshore wind
Capacity
5 MW
Status
Application Refused (Planning Permission Refused)
Operator or applicant
Pennant Walters
Location
Land near Bodelith Isaf, Llandderfel, Bala, Gwynedd, LL23 7LA
Turbines
2
  • 9 April 2014 Planning application submitted
  • 19 October 2015 Planning permission refused

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0790, Nordex attributes a Welsh wind turbine collapse to an overspeed condition, 74 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-07902022Nordex attributes a Welsh wind turbine collapse to an overspeed condition74 kmMajor
EIR-07322026Nordex turbine damaged by suspected lightning strike at UK wind farm102 kmMinor
EIR-16242026Crane topples on Scout Moor wind farm project119 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near LL23 7LA is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Gwynedd.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.