Bluewater Shopping Centre, Upper Thames Walk - Solar Photovoltaic Panel

Awaiting Construction1.3 MWApplication 22/01497/FULSubmitted 24 January 2023Granted 6 April 2023

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
22/01497/FUL
Planning authority
Dartford
County or area
Kent
Nation
England
Technology
Solar
Capacity
1.3 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Land Securities Property Limited
Location
Bluewater Shopping Centre Upper Thames Walk Bluewater Greenhithe, DA9 9ST
  • 24 January 2023 Planning application submitted
  • 6 April 2023 Planning permission granted
  • 6 April 2026 Planning permission expired

The pack for this site lists 89 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-1173, Rooftop solar panel fire on residential block in Lewisham, London, 20 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-11732024Rooftop solar panel fire on residential block in Lewisham, London20 kmSignificant
EIR-15302023Electrical fault causes solar panel fire in Wickford house26 kmMinor
EIR-13052017Fire at Thornton Heath flats reported to have been caused by an overheated solar panel26 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 86 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near DA9 9ST is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Dartford.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.