Blown transformer causes brief power outage for nearly 4,000 Fort Pierce customers
2020Published 6 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in the United States, and an email when EIR-2082 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Fort Pierce Utilities Authority
What happened
On 23 June 2020 a bushing failed on a transformer at a Fort Pierce Utilities Authority substation, briefly cutting power to around 3,800 customers. Utility staff switched supply to an alternate transformer and restored service within minutes. No fire, injury or evacuation was reported.
Contributing factors
Not reported.
Lessons learned
- Rapid transfer to a spare transformer limited the duration of the outage.
- Utilities should maintain the ability to switch load quickly when a single transformer fails.
More lessons on outages, backup supply and restoration, from every incident on the register.
Source
Published 2026-10-06. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.